110m stretch in to Pity Me to get big pavement/parking improvement

As many will have seen, the construction of the new footpath and cycleway we secured along the Framwellgate moor/Pity Me bypass is well under way. It occurred to us that if the work was extended into Pity Me, the long overdue improvement to the village could take place and be done cheaper.

We asked the council if they would pay for this and they refused, so we asked if they would contribute to the costs if we used local neighbourhood budgets towards it but they also refused.

Finally after repeated requests we got a price for the works which will save over £12,000 compared to this work being done separate to the Bypass works. So the 110m stretch of path from the roundabout to Potterhouse Terrace will now be resurfaced and rebuilt. The only bit not being done is the stepped area in front of the pub which we hope the Council will look to fund in the future.

We continue to be committed to improving the other side of the road too where the grassed area is in need of verge hardening as due to the lack of parking space, there is frequent parking. We are also working on improvements in other areas including on Framwellgate Moor Front Street.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.